Concrete Tear-Out & Replacement Timeline

By Henry Concrete — Mountain View, CA

Concrete replacement involves more steps than most homeowners anticipate. Understanding the timeline before the project starts prevents scheduling conflicts.

Day 1: Demolition

Existing concrete is broken out using jackhammers, breakers, or a skid-steer. The rubble is loaded onto a haul truck. Demolition creates significant noise and vibration — neighbors should be informed in advance.

Day 1-2: Haul-Off and Base Inspection

After demo, the existing base is exposed and inspected. If soft spots, contamination, or drainage issues are discovered, regrading and compaction work extends the prep phase.

Day 2: Base Prep and Forming

Gravel base and compaction where needed. Forms are set to establish the finished grade and slope. Rebar or wire mesh is placed as specified.

Pour Day: Concrete Placement and Finishing

The concrete truck arrives and pours into the formed area. The concrete is screeded, floated, and finished. For broom finish, the finishing sequence ends with the broom pass. Most residential pours take a full day.

Cure Period: 24 Hours to 28 Days

Light foot traffic is safe at 24-48 hours. Vehicle access for passenger cars should wait 7 days minimum. Heavy vehicles should wait the full 28-day cure.

Related: Concrete Replacement service · Process overview · Pricing · FAQ

Get Started

Ready to plan your concrete project?

Henry Concrete helps Mountain View-area homeowners understand scope, cost, and timeline before any work begins.